Architectural membranes / Procurement worksheet

Prepare an Architectural Membrane Material Specification

Turn your design brief into a comparable material inquiry. This architectural membrane specification template helps architects, contractors and fabricators record project requirements, evidence, supply scope and approval responsibilities. Complete the browser worksheet or download the editable Word template to prepare a membrane RFQ checklist.

White tensile canopy with raised peaks in DERFLEX website imagery
Application reference from the DERFLEX website. The specification must identify the material and project scope independently.
Procurement information. Record the design basis supplied by the responsible engineer. The worksheet contains no universal design strength, material class or compensation percentage.
Focus PVC-coated polyester architectural membranesFor Design, fabrication and procurement teams

Define the project

Project Brief

Start with the project’s function and decision makers. A permanent entrance canopy, a public roof and a replaceable shade element may require different evidence and supply interfaces. Describe the use before asking a supplier to propose a grade.

Project brief: establish the basis of the material inquiry
Brief fieldWhat to provideWho defines or reviews it
Project and applicationLocation, intended use, design programme and the element being procured.Client / architect / contractor.
Issued referencesDrawing numbers, revisions, specification issue and engineer’s requirements.Design team and document controller.
Exposure and accessRelevant climate, pollution, cleaning access and maintenance constraints.Design team and building operator.
Material and appearanceProposed grade or open brief, color reference, surface on each face and approved sample identity.Specifier with material reviewer.
Order scopeQuantity, useful width requirements, delivery point, timing and separately priced scope.Buyer and supplier.

On smaller screens, scroll the table horizontally to read every field.

Use the architectural membrane overview to confirm the material route. For PVC-coated polyester, start with the PVC architectural membrane product page. Record PTFE or ETFE as a different material system if specified; do not silently substitute one route for another.

State comparable requirements

Mechanical Requirements

Write each mechanical requirement as a complete comparison field: property, test method and edition, specimen condition, loading direction, unit, value basis and acceptance criterion. The engineer or designated reviewer sets the required performance. The supplier responds with the proposed grade and the evidence that supports it.

Mechanical fields: no universal numerical thresholds are prefilled
Requirement familyFields to carry into the specificationDecision to retain
Material identificationReinforcement, coating, nominal mass, thickness, surface system and roll-width basis.Proposed grade and declared tolerances, separately from design criteria.
Tensile and tear evidenceWarp / weft, method, unit, specimen and conditioning, statistical or declared value basis.Comparable result and reviewer’s acceptance reference.
Biaxial characterizationRequested protocol, loading ratios, sequence, material identity and report format.Responsible designer’s assessment of suitability for analysis or patterning.
Seams and adhesionProposed seam geometry, surface preparation, test direction, conditions and failure observations.Approved procedure and project-specific acceptance criteria.
Long-term requirementsRelevant temperature, sustained loading or exposure requirements and evidence requested.Engineer’s treatment of time-dependent behaviour and design assumptions.

On smaller screens, scroll the table horizontally to read every field.

Keep design outputs under design control. Prestress, design resistance, reduction factors, stiffness interpretation and pattern compensation belong to the responsible designer’s work. Reference the issued document; do not infer them from GSM or a breaking-strength value.

The tensile membrane selection guide provides the broader selection context. The architectural membrane GSM guide explains why weight is only one identity and procurement field.

Match evidence to the variant

Fire and Optical Data

Separate fire documentation, optical intent and surface appearance. A white sample does not establish a fire classification or a measured light-transmission value. For each requirement, identify the exact material variant and the evidence the project reviewer needs.

Fire documentation

State the required test or classification system, edition, project location and end-use conditions. Request the actual report or classification scope for the proposed grade, mass or thickness, finish and color. Record the reviewer who accepts its relevance.

Light and solar properties

Name the property to be compared, its method and unit, the color and face, and the specimen conditions. Distinguish visible light transmission from solar performance. Reference measured evidence rather than estimating from a rendering.

Surface and color

Record exterior and interior finishes separately, the color reference, appearance under the agreed light and the approved sample identifier. Identify any effect on welding preparation and cleaning requirements.

Durability and maintenance

Describe the exposure and requested evidence, including retained properties where relevant. Record the scope of written maintenance instructions and any offered warranty separately from the project’s design-life objective.

When discussing surface variants, use the PVC versus PVDF membrane comparison and PVDF lacquered membrane information to define the finish being requested. Do not transfer evidence from one variant to another without a documented scope check.

Define the purchase boundary

Fabrication Scope

Specify the boundary of the material purchase before comparing prices. An RFQ for rolls has different deliverables from an RFQ for cut or welded panels. Identify engineering, hardware, structure and installation as separate responsibilities and confirm any additional services in writing.

Fabrication and delivery: make scope comparable
Scope itemRecord in the RFQInterface to resolve
Roll materialGrade, useful width, quantity basis, finish, color, batch records and packing.Who controls nesting, yield and fabrication allowances?
Cut or fabricated panels, if requestedPanel references, drawing revision, edge details, face orientation and inspection requirements.Which fabrication tasks are actually included in the quotation?
Seam qualificationMaterial variant, process proposal, equipment, trial records and acceptance reference.Who approves the trial before production?
Fixings and supporting structureReferenced details, separately identified hardware and agreed supply exclusions.Who verifies the compatibility of membrane, edges and supporting system?
Packing and deliveryRoll or panel labels, protected faces, batch allocation, delivery location and documentation.Who checks the identity and condition at receipt?

On smaller screens, scroll the table horizontally to read every field.

Request grade-specific processing information and record the weld trial rather than prescribing a universal temperature or overlap. Any substitution in the finish, base fabric, process or seam geometry should return to the agreed review route.

Assign the review route

Submittal and Approval

Make every submittal traceable to the proposed supply and the issued specification. The approval record should show what was reviewed, by whom, against which requirement and with which open items. A supplier’s response and a project approval are different records.

  1. Issue the inquiry. Assign a revision and include the referenced drawings, requirements and document list.
  2. Receive the proposal. Record the grade, sample identity, scope, evidence provided and written deviations.
  3. Review and qualify. Have the appropriate reviewers assess material, fire, optical and fabrication evidence.
  4. Release the purchase. Carry the approved identity, document references and inspection plan into the order.
  5. Control changes. Review substitutions and superseded files before they affect production or delivery.

Use the architectural membrane technical resources page to organise a grade-specific document request. Until a file is issued, keep its revision and applicability open rather than inventing a document number.

Before you order

Resolve who approves the material, who qualifies seams, who releases fabrication drawings and who checks delivery records. Confirm the required sample, document language, quantity basis and shipment scope. Keep unresolved design requirements visible in the RFQ so quotations do not hide different assumptions.

Complete and download

Your Material Specification Worksheet

The blank Word attachment contains the procurement fields and editable text controls. The browser worksheet offers a quick text export of the same requirement groups. Neither route selects a grade or submits an inquiry automatically.

Complete the information you have. The export leaves missing items visible as “Not provided”. Your entries stay in this page until you close or reload it; nothing is sent automatically.

Project brief
Material and mechanical requirements
Surface, fire and optical evidence
Fabrication and delivery scope
Submittal and approval
Download blank Word template

Download your completed record first, then use the inquiry page to share the project requirements and arrange the supporting documents.

Common specification questions

Architectural Membrane Specification FAQ

What belongs in an architectural membrane specification?

Include the project use and location, drawing revision, material identity, engineer-defined mechanical requirements, fire and optical documentation, surface and color, seam qualification, inspection records, delivery scope and approval responsibilities. State the test method, unit, direction and acceptance basis wherever a property will be compared.

Can the template choose a membrane grade or design strength for me?

No. The template organizes procurement requirements. The project engineer defines the structural design basis and acceptance criteria. DERFLEX can be asked to propose a material against that brief, with supporting documents and declared deviations for review.

Should I specify only GSM and thickness?

No. These fields help identify the construction but do not establish its structural performance. Include reinforcement, directional mechanical data, test methods, surface system, seam evidence and the project reviewer’s requirements. Keep mass and thickness as separate fields.

Who defines pattern compensation and prestress?

The responsible structural or patterning designer defines these using the relevant project model, material data and agreed testing procedure. Leave the fields open until that work is completed. A generic percentage or uniaxial breaking result is not a substitute for the required material characterization.

Does the downloadable Word file include engineering calculations?

No. It is an editable procurement worksheet with blank fields and document-control prompts. It contains no preselected design strength, compensation percentage or material class. Reference the engineer’s issued calculations and drawings as separate controlled documents.

How do I use the browser worksheet?

Complete the fields you know and export the specification as a text file. Uncompleted fields remain identified as not provided. Download the Word template if you prefer an editable document, then use the DERFLEX inquiry page to share your requirements. The worksheet does not submit or upload information automatically.